Background
The National e-Governance Plan (NeGP) of the Govt. of India aims to make all Government services accessible to the common man in his locality, through Common Service Centers(CSCs) and ensure efficiency, transparency & reliability of such services at affordable costs to realize the basic needs of the common man. One of the goals of the Government to meet this vision is the need to cooperate, collaborate and integrate information across different departments in the Centre, States and Local Government. The State e-Governance Service Delivery Gateway (SSDG), a core component in e-Governance infrastructure under the NeGP, can simplify this task by acting as a standards-based messaging switch and providing seamless interoperability and exchange of data across.
Implementation of “State Portal, State Service Delivery Gateway and Electronic Forms” Scheme in Tamil Nadu
Project Overview
Government of Tamil Nadu desires to create an integrated information infrastructure that will expand, integrate and enhance the utility and reach of the services provided by the Government by utilizing the network of the Common Service Centres. DIT has already empanelled five implementing agencies through a central empanelment process. The State will select one of the implementing agencies among these five empanelled agencies and entrust the implementation of the project. These implementing agencies will be responsible for implementing the project in the State.
SSDG Conceptual Architecture

Project Components
The basic components of the project are as follows:
i. State Portal and Content Management System(CMS)
ii. electronic forms
iii. State Service Delivery Gateway (SSDG) Stack
iv. Training and Manpower for SSDG, State Portal , CMS, e forms and Gap Infrastructure
v. Infrastructure requirements for State Portal
vi. Computing Infrastructure at the destination offices including gaps in connectivity
vii. Compliance/Certification by STQC
Stake Holders
i. Department of Information Technology
ii. State Nodal Agency
iii. State Departments
iv. National Informatics Center
v. Center for Development and Advanced Computing (CDAC)
vi. Content Service Provider (CSP)
vii. Implementing Agency (IA)
viii. STQC
ix. Consultant
Project Consultants
M/s Infrastructure Leasing and Financial Services Limited have been appointed as Consultants to assist the State Government in the following activities:
a.) Preparation of a Detailed Project Report to identify the Infrastructure Gap in the respective line departments and to carry out an AS-IS study of the process involved in delivering services identified under the project
b.) Preparation of Request for Proposal to select an Implementing Agency
c.) Assist the State in Bid Process Management
d.) Project Monitoring
Project Outlay
Government of India has sanctioned Rs.16.13 crores towards implementation of the Tamil Nadu State Portal, TNSSDDG and Electronic forms.
Current Status
a) National Informatics Center, Tamil Nadu has been entrusted with the work of development of State Portal and Content Management System
b) State Project Committee to oversee the implementation of the SSDG projects constituted in GO Ms No.7, IT Dept dated 09.03.2010.
c) The SPC meeting was held on 15.04.2010 and the RFP for selection of Implementing Agency approved by the SPC, RFP has been circulated to empanelled agencies on 07.05.2010.
d) Pre Bid meeting with empanelled agencies held on 18.05.2010.
e)Technical Evaluation of eligible bidders done by Technical committee.
f)Price bids have been opened and negotiation initiated with L1 bidder for best prices and best value to the project.
Progress Report on State Portal and SSDG Implementation
State Nodal Agency : M/s. Tamil Nadu e-Governance Agency
SSDG Consultants : M/s. Infrastructure Leasing and Financial Services Limited
| Pre Project Initiation Phase | |||
|---|---|---|---|
| S.No | Description of Activity | Agency Involved | Completion Date |
| 1 | Budgetary Proposal sent to DIT | TNeGA | 13.03.2009 |
| 2 | Administrative Approval from GoI | DIT | 30.03.2009 |
| 3 | Approval on Services / Budget / Empanelled Implementing Agencies | DIT | 16.04.2009 |
| 4 | Workshop on Project Implementation | TNeGA/NIC/IL&FS | 11.05.2009 |
| 5 | Communication on Empanelled Agencies for Selection of Consultants | DIT | 03.07.2009 |
| 6 | Communication on Primary / Secondary choice of Consultants sent to DIT | TNeGA | 15.07.2009 |
| 7 | Confirmation on primary Choice on Engagement of Consultant | DIT | 16.07.2009 |
| 8 | Orders from GoTN appointing TNeGA as Nodal Agency | GoTN | 06.08.2009 |
| Project Initiation Phase | |||
| S.No | Description of Activity | Agency Involved | Completion Date |
| Phase I - Preparation of Detailed Project Report | |||
| 1 | Engagement of Consultant | TNeGA | 24.08.2009 |
| 2 | Communication from TNeGA to the identified departments | TNeGA | 05.09.2009 |
| 3 | e-form proof of concept presentation/workshop | DIT/TNeGA/NIC/Cdac/IL&FS/Wipro | 10.09.2009 |
| 4 | Execution of Project Engagement Agreement | TNeGA/IL&FS | 15.09.2009 |
| 5 | Inception Report | IL&FS | 06.10.2009 |
| 6 | Infrastructure Gap Analysis of Eleven Departments | IL&FS | 07.11.2009 |
| 7 | Process Mapping of Services Identified | IL&FS | 09.11.2009 |
| 8 | Functional Requirement Specifications | IL&FS | 10.11.2009 |
| 9 | Functional Requirement Specifications- Inputs from NIC on State Portal | NIC | 12.11.2009 |
| 10 | e-form proof of concept - VC | DIT/TNeGA/NIC/Cdac/IL&FS/Wipro | 16.11.2009 |
| 11 | Sign-off from respective Departments on Gap Analysis & Process Mapping | IL&FS/Line Departments | 18.11.2009 |
| 12 | Detailed Project Report | IL&FS | 18.11.2009 |
| Phase II - Preparation of Draft RFP and required Approvals | |||
| 13 | Bill of Materials - Gap Infrastructure, SSDG, State Portal | IL&FS/Cdac/NIC | 30.11.2009 |
| 14 | Draft Request for Proposal | IL&FS | 01.12.2009 |
| 15 | Circulation of Draft RFP to NIC | TNeGA | 01.12.2009 |
| 16 | Engagement of NIC for State Portal Development | TNeGA | 02.12.2009 |
| 17 | Inputs / Feedback from NIC | NIC | 09.12.2009 |
| 18 | Training / Workshop on e -forms | Cdac / NIC | 08/09.12.2009 |
| 19 | Review by TNeGA | TNeGA | 14.12.2009 |
| 20 | Finalization of RFP | TNeGA | 18.12.2009 |
| 21 | RFP forwarded to DIT for Approval | TNeGA | 21.12.2009 |
| 22 | Communication from DIT on Formation of State Project Committee | DIT | 24.12.2009 |
| 23 | Draft GO sent to IT Secretary for Approval and Issuance | TNeGA | 06.01.2010 |
| 24 | Draft RFP Circulated to eleven Line Departments | TNeGA / Consultant | 19.02.2010 |
| 25 | Proposal from NIC for design & development of State Portal & CMS | NIC | 02.03.2010 |
| 26 | Formation of State Project Committee | GoTN | 09.03.2010 |
| 27 | Nodal Officers Workshop | TNeGA/Consultant | 07.04.2010 |
| 28 | SPC meeting for Approval of RFP | TNeGA / SPC | 15.04.2010 |
| 29 | Approval of SPC Minutes for Issue of RFP | State Project Committee | 15.04.2010 |
| Phase III - Selection of Implementing Agencies | |||
| 30 | Issuance of RFP | TNeGA | 07.05.2010 |
| 31 | Pre-Bid Meeting | TNeGA | 18.05.2010 |
| 32 | Issue of Corrigendum 1 based on Pre-Bid Meeting | TNeGA | 27.05.2010 |
| 33 | Issue of Corrigendum 2 | TNeGA | 28.05.2010 |
| 34 | Last Date for Submission of Tender | Empanelled Implementing Agencies | 14.06.2010 |
35 |
Technical Presentation |
Bidders / NIC / CDAC / TNeGA / Consultant |
30.06.2010 |
36 |
Technical Bid Evaluation |
NIC / CDAC / TNeGA / Consultant (IL&FS) |
30.06.2010 |
37 |
Commercial Bid Opening & Bid Results |
Bidders/TNeGA/Consultant (IL&FS) |
02.07.2010 |
| State Portal & Content Management System - Progress | |||
|---|---|---|---|
| 1 | Proposal from NIC for Design & Development of State Portal & CMS | NIC | 02.03.2010 |
| 2 | Issue of work order for State Portal & CMS | TNeGA | 11.03.2010 |
| 3 | Transfer of Funds to NIC | TNeGA | 11.03.2010 |
| 4 | State Portal Demo | NIC | 10.06.2010 |
| 5 | State Portal completion of testing | STQC | 1.02.2012 |
| Selection of Content Service Provider | |||
|---|---|---|---|
| 1 | Issue of RFP for Selection of CSP for NP & State CSP | TNeGA | 28.02.2010 |
| 2 | Pre-Bid Meeting | TNeGA | 10.03.2010 |
| 3 | Minutes of Pre-Bid Meeting | TNeGA | 15.03.2010 |
| 4 | Issue of Corrigendum 1 | TNeGA | 18.03.2010 |
| 5 | Issue of Corrigendum 2 | TNeGA | 24.03.2010 |
| 6 | Last Date for submission of Bids | Bidders | 26.03.2010 |
| 7 | Opening of Technical Bids | TNeGA | 26.03.2010 |
| 8 | Technical Evaluation | Consultant / TNeGA | 22.04.2010 |
| 9 | Presentation to Evaluation Committee | Bidders | 23.04.2010 |
| 10 | Technical Evaluation scores sent to NIC | TNeGA | 05.05.2010 |
| 11 | Final Approval from Technical Committee | Technical Committtee | 18.05.2010 |
| 12 | Opening of Price Bids | TNeGA/Consultant /Bidders | 19.05.2010 |
| 13 | Tender Results Published | TNeGA | 21.05.2010 |
| 14 | Confirmation from L2 & L4 matching L1 for State Portal quotes | Bidders | 24.05.2010 |
| 15 | Execution of Agreement between State and CSP | TNeGA / Onward eServices Limited | 06.09.2010 |
| Phase IV - Impelemtation Phase Deliverables | |||
| 1 | Provided in puts on process mapping, DPR and other documents and shared the same with the IA. | IL&FS | 10.11.2010 |
| 2 | Comments on the SRS prepared by the IA given to State Nodal Agency | IL&FS | 8.11.2010 |
| 3 | Integration of services with SSDG review meetings. 1st meeting held | TNeGA/NIC/Cdac/IA/IL&FS | 10.11.2010 |
| 4 | Assisted the IA in developing module for State Level Work shop on SSDG | IL&FS | 16.11.2010 |
| 5 | Integration of services with SSDG review meetings. 2nd meeting held | TNeGA/NIC/Cdac/IA/IL&FS | 6.12.2010 & 8.12.2010 |
| 6 | Letter of Indent for SSDG/SP hardware requirement | TNeGA | 16.12.2010 |
| 7 | SSDG feedback form on Consultancy sent to DIT | TNeGA | 3.1.2011 |
| 8 | Review of end to end testing of one service | Cdac/TNeGA/NIC | 19.1.2011 |
| 9 | SRS of IA approved by TNeGA | TNeGA | 24.1.2011 |
| 10 | Deputing one Scientist from Cdac to NIC for sorting out installation issues of SSDG stack | Cdac/TNeGA/NIC | 24.1.2011 |
| 11 | Integration issues regarding Civil Supplies Review | TNeGA/IA/IL&FS/Onward eServices | 28.1.2011 |
| 12 | MSA signed between IA /State/TNeGA | TNeGA/IA | 28.2.2011 |
| 13 | Letter of support to IA pending signing of MSA | TNeGA | 1.3.2011 |
| 14 | Involved in the development of training module of the IA at the District level. Trichy district workshop held | IL&FS/Wipro | 1st to 3rd April, 2011 |
| 15 | TNSDC and SSDG integration review | TNeGA/ELCOT/NIC/Wipro/PWC | 18.3.2011 & 1.4.2011 |
| 16 | Submission of STQC testing proposals | STQC | 5.4.2011 |
| 17 | Software requirement for State Portal Purchase order issued | TNeGA | 3.6.2011 |
| 18 | STQC Testing proposals approved | TNeGA | 14.6.2011 |
| 19 | Hardware installation report validated in respect of Racks, witches and Monitors | IL&FS/IA | 22.6.2011 |
| 20 | Proposals sent to Government for data conversion, font conversion issues of Civil Supplies Department in two districts approved by State Planning Commission | TNeGA | 23.6.2011 |
| 21 | SSDG Status review | TNeGA with Stake holders | 30.6.2011 |
| 22 | SSDG Status review | TNeGA with Stake holders | 26.7.2011 |
| 23 | State Portal Review by Apex Committee | Chief Secretary | 23.02.2012 |
| MILESTONES OF IMPLEMETING AGENCY | |||
|---|---|---|---|
| 1 | Letter of Acceptance (LoA Issuance) | 04-Sep-2010 | |
| 2 | Execution of Agreement (MSA) | 25-Feb-2011 | |
| 3 | Project Kickoff Meeting | 13-Sep-2010 | |
| 4 | Assessment and validation of physical infrastructure assets at SDC / SWAN PoC and Gap Infrastructure details from the point of view of installation of IT hardware for Portal and SSDG | 28-Oct-2010 | |
| 5 | Supply of hardware (servers & PCs), system software, peripherals and other accessories to the State HQs & customer premises | Supply of servers to SDC completed | |
| 6 | Sign off on SRS | 5-Nov-2010 | |
| 7 | Conversion of Physical forms to eForms | 25-Nov-2010 | 35 standalone e-Forms are developed |
| 8 | Application Development of eForms (Total Identified Departments - 11; Total Identified Services-53; Services under e-District-11; Services planned for Go-Live-3) | 35 standalone forms developed. | |
| Integration Phase 1 - e-District Services of NIC (10 services) | Integration completed for 10 services | ||
| Integration Phase 2 - Other Services of NIC | 11 services planned | ||
| 9 | Site survey for Gap Infra installation | 22-Mar-2011 | |
| 10 | Installation of Infrastructure at State Headquarters | 22-June-2011 | Signed off by NIC and CDAC |
| 11 | Installation and commissioning of hardware, system software, peripherals and other accessories | Awaiting PO for supply of Gap Infrastrucutre | |
| 12 | Network – Broad Band connectivity for all locations | ||
| 13 | Security Implementation | STQC has completed security audit on staging environment | |
| 14 | Design documentation and manuals for end users | Completed by Wipro & NIC | |
| 15 | Development of State Portal by NIC | 1-Feb-2012 | STQC has completed functional and security testing on State Portal and CMS |
| 16 | Integration with State Portal | 1-Feb-2012 | |
| 17 | Trial Run, Test Run , User Acceptance Test | ||
| 18 | QC feedback incorporation and re-certification, if required | ||
| 19 | Quality Certification (STQC) | Functional and Security testing completed for, State Portal, CMS,e-Forms(10 services) | |
| 20 | Go-Live | ||
| State Portal | To be decided after load testing | ||
| SSDG | The production environment to be load tested by STQC. | ||
| 21 | Trainings - Capacity Building | Trainings completed for 3500+ employees | |
List of Departments and Services Identified for Tamil Nadu
S. No. |
Name of Department |
Services |
|
|---|---|---|---|
1 |
Agriculture Marketing | 1.1 | Market information on Commodity requirement |
1.2 |
Welfare Scheme details & Benefits extended |
||
1.3 |
Beneficiary eligibility criteria |
||
1.4 |
Market rate of commodities |
||
2 |
Civil Supplies & Consumer Protection |
2.1 |
New Card Application |
2.2 |
Changes in Ration Card |
||
2.3 |
Complaints |
||
2.4 |
FPS related information(Allotment-A Regr) |
||
3 |
Registration |
3.1 |
Application for E.C |
3.2 |
Application for Certified Copies |
||
3.3 |
Application for Marriage Certificate |
||
4 |
Employment |
4.1 |
Registration for employment |
4.2 |
Renewal/transfer of Regn |
||
4.3 |
Information Dissemination |
||
4.4 |
Career guidance |
||
5 |
School Education |
5.1 |
Parents-Information |
5.2 |
Students Information-Timetable, Results, Syllabus, Scholarship, Exam fees |
||
5.3 |
Teachers-PF/loan/salary/form download |
||
6 |
Municipal Administration |
6.1 |
Issue of Birth & Death Certificate |
6.2 |
Collection of Taxes |
||
6.3 |
Online Payment of Taxes |
||
6.4 |
Verification of birth/Death etc details |
||
7 |
Tribal Welfare |
7.1 |
Dissemination of Tribal Welfare Scheme |
7.2 |
Application for Enrollment in the Scheme |
||
7.3 |
Skill Development Scheme |
||
8 |
Town Panchayat |
8.1 |
Birth and Death Certificate |
8.2 |
Property Tax |
||
8.3 |
Water Charges |
||
8.4 |
Profession Tax |
||
9 |
Social Welfare |
9.1 |
Information on welfare schemes |
9.2 |
Forms download (18 forms--tn.gov-ser-forms) |
||
9.3 |
Complaints |
||
9.4 |
Report from NGOs |
||
10 |
Revenue |
10.1 |
Issuance of Community/Nativity/Legal Heir ship/ Solvency/Birth/Death (in Village Panchayat)/Income/ Destitute Widow/ Inter caste marriage/Deserted women/ No graduate Certificate (11 cases) |
10.2 |
Sanction of Pensions--Old age & other various schemes & \Sanction of financial Assistance under various schemes |
||
10.3 |
Issuance of Certificate for Destitute Children for admission in Orphanage School |
||
11 |
Survey & Settlement |
11.1 |
Issue of Patta Extract |
11.2 |
Mutation of Land records |
||
11.3 |
Patta transfer |
||
11.4 |
Issue of Adangal |
||